Projects

Ermak Modular Electrical Cluster Drilling Rig of Walking Type

Year:  2008

Number:  1

Total weight:  1,400 ton

The Ermak modular electrical cluster drilling rig of walking type capable of drilling down to 6,500 m deep was built under a turn-key contract for Eurasia Drilling Company. This is the first drilling rig produced in Russia that moves with the use of a special hydraulic walking system. This solution, as compared against the rig movement systems based on guide beams, provides for the rig movement not only forwards/backwards but also sidewise and to 360° about its vertical axis.

Other projects

Upgrading of drilling rigs
Within upgrading of train-type drilling rigs, OOO Kliver produces mast and substructure units of 200 ton capacity capable of drilling with a top drive.
Fabrication of modules of a natural gas treatment unit and fabrication of piping for the Vysotsk LNG plant
Manufacturing of natural gas treatment unit modules for the LNG production and offloading terminal in the Vysotsk seaport in the Leningrad Region.
A set of large-diameter shells and inserts for the liquefied natural gas receipt and storage terminal
In November 2016, OOO Kliver was awarded a contract by JSC MRTS for fabrication of 22 off inserts and 4 sets of large-diameter shells within the project of construction of the Liquefied Natural Gas (LNG) Receipt, Storage and Regasification Terminal in the Kaliningrad Region.
Manufacture of 2 sets of a drilling rig BU E BM K-320
In 2015, OOO Kliver launched manufacture of BU E BM K-320 Kliver Cluster Slider drilling rigs of 320 ton capacity designed by Bentec GmbH Drilling and Oilfield Systems, Germany.
Slipway cradles for a large-size ship launching system – 8 units
Manufacture of non-standard equipment for a large-size ship launching system at the Sevmash shipyard.
Manufacture of module steel structures of the SP38 work package
In 2017, OOO Kliver became the unique company in Russia having experience in the turn-key manufacture of process modules for the Yamal LNG project, the largest integrated project in Russia for production, liquefaction and delivery of natural gas.
A derrick for an offshore drilling rig operating on the Arkutun-Dagi oil field within the Sakhalin-1 project
Fabrication of a drilling rig derrick of 650 ton capacity for an offshore drilling platform operated on the Arkutun-Dagi oil field within the Sakhalin-1 project.
Steel structures of a pedestrian bridge (200 m long) for Oslo, Norway
In 2009, the Kliver yards fabricated a 200 m pedestrian bridge ordered by SIAS, Norway, to connect an old and a recently developed areas downtown Oslo.
LSP-2 Fixed Offshore Ice-Resistant Living Quarters Platform
Turn-key construction of the LSP-2 fixed offshore ice-resistant platform (living quarters) and a connecting bridge for the Y. Korchagin oil field in the Caspian Sea.
Varandey Fixed Offshore Ice-Resistant Off-Loading Terminal
It had taken 15 months, from late March 2006 to July 1, 2007, for the Kliver yards to construct the Varandey fixed offshore ice-resistant off-loading terminal weighing about 14,000 ton.